LK Automation Limited LK Automation Limited
Information sort OMRON | MITSUBISHI | Proface | Mennekes | Yaskawa
Home >> Supply
A0J2-C03F Connecting cable MITSUBISHI A0J2-C03F Depending on the way the field signals are generated,


Parallel printer connection (1CH).
Applicable models: A95_ (-M3) /A956WGOT. DC input points: 16 points.
Input voltage and current: 3/7mA, DC12/24V.
Response time: 10ms.
16 point /1 a public side.
Positive pole sharing.
Output points: 12 points.
Output voltage and current: DC24V/AC240V, 2A/1 point, 5A/1 common end A0J2-C03F.
Response time:: 12ms.
8 point /1 a public end, 3 point /1 a common end, independent contact.
Output form: relay output.
36 point terminal station.
Number of stations: 4 stops A0J2-C03F.
Compact remote I/O unit.
According to the control requirements of the system, using the appropriate design method to design MITSUBISHI PLC program.
Procedures to meet the requirements of system control as the main line,
Write one by one to achieve the control function or the sub task of the program,
Gradually improve the functions specified by the system A0J2-C03F.
MITSUBISHI PLC detection, fault diagnosis and display and other procedures.
These procedures are relatively independent, generally in the basic completion of the program design and then add MITSUBISHI A0J2-C03F.
Hardware simulation method is to use a number of hardware equipment to simulate the generation of the signal,
The signals are connected to the input end of the PLC system in a hard wired way, and the timeliness is strong.
Software simulation method is in the MITSUBISHI PLC in the preparation of a set of simulation program,
The simulation provides the field signal, which is simple and easy to operate, but it is not easy to guarantee the timeliness MITSUBISHI A0J2-C03F.
Simulation of the process of debugging, debugging method can be used to segment, and the monitoring function of programmer MITSUBISHI A0J2-C03F.
A0J2 56.
Input / output unit 2
MITSUBISHI PLC program simulation debugging
The basic idea of program simulation debugging is,
In order to facilitate the form of simulation to generate the actual state of the scene,
Create the necessary environmental conditions for the operation of the program.
Depending on the way the field signals are generated,
The simulation debugging has two forms of hardware simulation and software simulation. Master / local station.
AnCPU use.
According to the control requirements of the system, using the appropriate design method to design MITSUBISHI PLC program.
Procedures to meet the requirements of system control as the main line,
Write one by one to achieve the control function or the sub task of the program,
Gradually improve the functions specified by the system.
MITSUBISHI PLC initialization procedure. After MITSUBISHI PLC on power, the general need to do some of the initial operation,
In order to start making necessary preparations, to avoid the wrrong operation of the system A0J2-C03F.
The main contents of the initialization program are: to some data area, counter and so on,
Data needed to restore some of the data area,
Set or reset some relays,
For some initial state display, etc.. "